Adapting to change takes time. For this reason, we are implanting the Time of Use rates gradually. Starting in March 2025 there will be an initial change in the rate, followed by a further adjustment in June, September and finally December. This approached is designed to give you ample time to adapt your energy usage to fully benefit from the new rate plan.
General Information for an Underground CT Cabinet Service
A CT cabinet is required on all services above 320 amps and 4-wire services over 200 amps (except when the pad mount is metered).
Meter Socket shall be mounted 5' above the finished grade.
CT cabinet shall be mounted so that the bottom is 2' above the finished grade.
Service is to be member-owned, meaning the member is to install service wire from the CT cabinet to the base of the pole, leaving approximately 40' at the base for KV REMC to connect at the pole top.